SLAB THICKNESS 22 CM

DOSAGE FIBRATEC V12-AM: 2 kg / m³

The máximum permisible static point load is 6460 kg

The Dynamic load for:

50 repetitions/day: 6460 kg

100 repetitions/day: 5985 kg

200 repetitions/day: 5320 kg

300 repetitions/day: 4940 kg

The recommended distances between the shrinkage joints are:

Indoor slab: 4,5m - 6m

Outdoor slab: 4,5m - 6m

Depth of cut joint: 7 cm

DOSAGE FIBRATEC V12-AM: 3 kg / m³

The máximum permisible static point load is 6800 kg

The Dynamic load for:

50 repetitions/day: 6800 kg

100 repetitions/day: 6300 kg

200 repetitions/day: 5600 kg

300 repetitions/day: 5200 kg

The recommended distances between the shrinkage joints are:

Indoor slab: 4,5m - 6m

Outdoor slab: 4,5m - 6m

Depth of cut joint: 7 cm