SLAB THICKNESS 19 CM
DOSAGE FIBRATEC V12-AM: 2 kg / m³
The máximum permisible static point load is 5130 kg
The Dynamic load for:
50 repetitions/day: 4988 kg
100 repetitions/day: 4608 kg
200 repetitions/day: 4133 kg
300 repetitions/day: 3800 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 4,25m - 5,5m
Outdoor slab: 4m - 5m
Depth of cut joint: 6 cm
DOSAGE FIBRATEC V12-AM: 3 kg / m³
The máximum permisible static point load is 5400 kg
The Dynamic load for:
50 repetitions/day: 5250 kg
100 repetitions/day: 4850 kg
200 repetitions/day: 4350 kg
300 repetitions/day: 4000 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 4,25m - 5,5m
Outdoor slab: 4m - 5m
Depth of cut joint: 6 cm