SLAB THICKNESS 13 CM
DOSAGE FIBRATEC V12-AM: 2 kg / m³
The máximum permisible static point load is 2850 kg
The Dynamic load for:
50 repetitions/day: 2565 kg
100 repetitions/day: 2375 kg
200 repetitions/day: 2138 kg
300 repetitions/day: 1995 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 3m - 3,5m
Outdoor slab: 2m - 3m
Depth of cut joint: 4 cm
DOSAGE FIBRATEC V12-AM: 3 kg / m³
The máximum permisible static point load is 3000 kg
The Dynamic load for:
50 repetitions/day: 2700 kg
100 repetitions/day: 2500 kg
200 repetitions/day: 2250 kg
300 repetitions/day: 2100 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 3m - 3,5m
Outdoor slab: 2m - 3m
Depth of cut joint: 4 cm