SLAB THICKNESS 12 CM
DOSAGE FIBRATEC V12-AM: 2 kg / m³
The máximum permisible static point load is 2470 kg
The Dynamic load for:
50 repetitions/day: 2233 kg
100 repetitions/day: 2090 kg
200 repetitions/day: 1853 kg
300 repetitions/day: 1710 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 3m - 3,5m
Outdoor slab: 2m - 3m
Depth of cut joint: 4 cm
DOSAGE FIBRATEC V12-AM: 3 kg / m³
The máximum permisible static point load is 2600 kg
The Dynamic load for:
50 repetitions/day: 2350 kg
100 repetitions/day: 2200 kg
200 repetitions/day: 1950 kg
300 repetitions/day: 1800 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 3m - 3,5m
Outdoor slab: 2m - 3m
Depth of cut joint: 4 cm