SLAB THICKNESS 22 CM

DOSAGE FIBRATEC V12-AM: 2 kg / m³

The máximum permisible static point load is 9595 kg

The Dynamic load for:

50 repetitions/day: 7885 kg

100 repetitions/day: 7268 kg

200 repetitions/day: 6508 kg

300 repetitions/day: 6033 kg

The recommended distances between the shrinkage joints are:

Indoor slab: 4,5m - 6m

Outdoor slab: 4,5m - 6m

Depth of cut joint: 7 cm

DOSAGE FIBRATEC V12-AM:3 kg / m³

The máximum permisible static point load is 10100 kg

The Dynamic load for:

50 repetitions/day: 8300 kg

100 repetitions/day: 7650 kg

200 repetitions/day: 6850 kg

300 repetitions/day: 6350 kg

The recommended distances between the shrinkage joints are:

Indoor slab: 4,5m - 6m

Outdoor slab: 4,5m - 6m

Depth of cut joint: 7 cm