SLAB THICKNESS 17 CM
DOSAGE FIBRATEC V12-AM: 2 kg / m³
The máximum permisible static point load is 6460 kg
The Dynamic load for:
50 repetitions/day: 5178 kg
100 repetitions/day: 4750 kg
200 repetitions/day: 4275 kg
300 repetitions/day: 3943 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 4m - 5m
Outdoor slab: 3,5m - 4m
Depth of cut joint: 5,5 cm
DOSAGE FIBRATEC V12-AM: 3 kg / m³
The máximum permisible static point load is 6800 kg
The Dynamic load for:
50 repetitions/day: 5450 kg
100 repetitions/day: 5000 kg
200 repetitions/day: 4500 kg
300 repetitions/day: 4150 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 4m - 5m
Outdoor slab: 3,5m - 4m
Depth of cut joint: 5,5 cm