SLAB THICKNESS 14 CM
DOSAGE FIBRATEC V12-AM: 2 kg / m³
The máximum permisible static point load is 4845 kg
The Dynamic load for:
50 repetitions/day: 3800 kg
100 repetitions/day: 3515 kg
200 repetitions/day: 3135 kg
300 repetitions/day: 2898 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 3,5m - 4m
Outdoor slab: 2,5m - 3,5m
Depth of cut joint: 4,5 cm
DOSAGE FIBRATEC V12-AM: 3 kg / m³
The máximum permisible static point load is 5100 kg
The Dynamic load for:
50 repetitions/day: 4000 kg
100 repetitions/day: 3700 kg
200 repetitions/day: 3300 kg
300 repetitions/day: 3050 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 3,5m - 4m
Outdoor slab: 2,5m - 3,5m
Depth of cut joint: 4,5 cm