SLAB THICKNESS 20 CM

DOSAGE FIBRATEC V12-AM: 2 kg / m³

The máximum permisible static point load is 9215 kg

The Dynamic load for:

50 repetitions/day: 7315 kg

100 repetitions/day: 6745 kg

200 repetitions/day: 6033 kg

300 repetitions/day: 5605 kg

The recommended distances between the shrinkage joints are:

Indoor slab: 4,25m - 5,5m

Outdoor slab: 4m - 5m

Depth of cut joint: 6,5 cm

DOSAGE FIBRATEC V12-AM: 3 kg / m³

The máximum permisible static point load is 9700 kg

The Dynamic load for:

50 repetitions/day: 7700 kg

100 repetitions/day: 7100 kg

200 repetitions/day: 6350 kg

300 repetitions/day: 5900 kg

The recommended distances between the shrinkage joints are:

Indoor slab: 4,25m - 5,5m

Outdoor slab: 4m - 5m

Depth of cut joint: 6,5 cm