SLAB THICKNESS 20 CM
DOSAGE FIBRATEC V12-AM: 2 kg / m³
The máximum permisible static point load is 9215 kg
The Dynamic load for:
50 repetitions/day: 7315 kg
100 repetitions/day: 6745 kg
200 repetitions/day: 6033 kg
300 repetitions/day: 5605 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 4,25m - 5,5m
Outdoor slab: 4m - 5m
Depth of cut joint: 6,5 cm
DOSAGE FIBRATEC V12-AM: 3 kg / m³
The máximum permisible static point load is 9700 kg
The Dynamic load for:
50 repetitions/day: 7700 kg
100 repetitions/day: 7100 kg
200 repetitions/day: 6350 kg
300 repetitions/day: 5900 kg
The recommended distances between the shrinkage joints are:
Indoor slab: 4,25m - 5,5m
Outdoor slab: 4m - 5m
Depth of cut joint: 6,5 cm